Iraq – Baghdad Al-Mansour
+964 750 352 3978
info@saheel-iq.com

All Projects

1- Saheel Almortajez Company projects for the year 2014.

#

 

Project name & Country

of Assignment

Client & Reference Contact Details Types of activities undertaken
1 Construction and installation of 6 type towers (XYA) and 2 type towers (CROSS  105 XB) the project for the Baiji Gas Station interconnection line. General Directorate of Electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng.Ali Mohammad Abdullah

aliabosedrah3@gmail.com

009647736998771

Transmission Line
2 Construction and installation of 6 type towers (XYA) and 1 type tower XYB, the project for the Baiji Gas Station interconnection line. General Directorate of Electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng.Ali Mohammad Abdullah

aliabosedrah3@gmail.com

009647736998771

Transmission Line
3 Construction and installation of 7 type towers (XYA) and 1 type tower XYB, the project for the Baiji Gas Station interconnection line. General Directorate of Electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng. Ibrahim Thamer Hamad

07701854540

Transmission Line
4 Carrying out concrete work pouring concrete works (materials + work) for Tower 1 No. 16 (0 + 0) XYD type for the Baiji Gas Station interconnection line 400 k.v – side Hadeetha 400 k.v. General Directorate of Electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng. Ibrahim Thamer Hamad

07701854540

Transmission Line
5 Carrying out concrete work pouring concrete works (material + work) for  3 Towers  No. (1-2-4) XD type for the Baiji Gas Station interconnection line 400 k.v.  – side Hadeetha 400 k.v. General Directorate of Electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng.Ali Mohammad Abdullah

aliabosedrah3@gmail.com

009647736998771

Transmission Line
6 Construction and installation of 1 type towers (XYC) No. 8 and the connection works for the wires from East Mosul 400 K.V station to Tower No.8 for East Mosul Line – Kirkuk side 400 k.V. General Directorate of electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng. Mohammed Idrees

alshafey73.yahoo.com

009647518094207

Transmission Line
7 Construction and installation of 1 type towers (XD) No. 10 and the connection works for the wires from East Mosul 400 K.V station to Tower No.10. General Directorate of electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng. Mohammed Idrees

alshafey73.yahoo.com

009647518094207

Transmission Line
8 Carrying out concrete work pouring concrete works (material + work) for 3 Towers No. (1-2-4) XYD type for the Baiji Gas Station interconnection line 400 k.v. –  Baiji Thermal Station 400 k.v. General Directorate of Electricity Transmission Projects / Implementation of Transport Lines Projects for the Northern Region.

Eng.Ali Mohammad Abdullah

aliabosedrah3@gmail.com

009647736998771

Transmission Line

 

2- Saheel Almortajez Company projects for the year 2015.

#

 

Project name & Country

of Assignment

Client & Reference Contact Details Types of activities undertaken
1 Renovation of roof rehabilitation for three schools in Domiz Camp With the participation of Haval United Company in Dohuk . OrganizationI.R.C  /

Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Rehabilitation  schools
2 Creation of a bridge( 2*2) along( 30 ml ) With the participation of Haval United Company in Dohuk. Directorate Roads and Bridges of Dohuk

Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Roads and Bridges works

3- Saheel Almortajez Company projects for the year 2016.

#

 

Project name & Country

of Assignment

Client & Reference Contact Details Types of activities undertaken
1 Rehabilitation of four schools in Duhok Governorate With the participation of Haval United Company. OrganizationI.R.C  /

Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Rehabilitation schools
2 Renovation of Four Schools in Duhok Governorate With the participation of Haval United Company. OrganizationI.R.C /

Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Rehabilitation schools
3 Extend water network line 4 km with Extend power grid line 1 km to the water station in Zummar District With the participation of Haval United Company. The Union Lutheran

Organization ( LWF ) /

Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Water and electricity lines works

4- Saheel Almortajez Company projects for the year 2017.

Project of rehabilitating the auxiliary eastern electricity station 132 K.V in the governorate of Nineveh. Directorate General of Electric Power Transmission -Northern Area.

Eng. Fadel Abbas /General Manager

07507991121

northtransmissionoffice@yahoo.com

Transmission Line  
Project of fixing, constructing, installing, and lining the falling towers on lines of Mansour-Yaremja (1,2) 132 K.V and a super pressure touch line –East of Mosul 400 K.V Directorate General of Electric Power Transmission -Northern Area.

Eng.Fadel Abbas /General Manager

07507991121

northtransmissionoffice@yahoo.com

Transmission Line  
project for repair towers type (XYA) of line (Nineveh gas station – station Baiji) k. v400 Directorate General of Electric Power Transmission -Northern Area.

Eng.Fadel Abbas /General Manager

07507991121

northtransmissionoffice@yahoo.com

Transmission Line  
Projects of implementing the maintenance of electric power transmission lines in the Northern Area according to the administrative order no. (1672) on 30/4/2017, among the other works by the Committee of Liberated Area in Nineveh in 2017.
Commitment to fix cuts in power transfer cables 132 K. V- south of Mosul Directorate General of Electric Power Transmission -Northern Area.

Eng.Fadel Abbas /General Manager

07507991121

northtransmissionoffice@yahoo.com

Transmission Line  
Commitment to fix cuts in cables of line Mansour-Mishraq 132 K. V = Transmission Line  
Commitment to fix cuts in cables type (Teal) in part of line (Mosul-Hammam 132K.V) from the special tower in Alma’mun quarter to super pressure Mosul station 400 K.V = Transmission Line  
Fixing cuts in cables of Almishraq line-Addaya 132 K.V = Transmission Line  
Commitment to convert, manufacture, and make converted tower poles using concrete for the lines (Mansour-Yaremja) 132 K.V = Transmission Line  
Commitment to change sets of insulators of line Qayarah-Shirqat 132 K.V = Transmission Line  
Fixing cuts in cables type (CAAA) in lines (Mosul 400-east of Mosul 400K.V) = Transmission Line  

5- Saheel Almortajez Company projects for the year 2018.

# Project name & Country

of Assignment

Client & Reference Contact Details Types of activities undertaken
1 Construction of Latrines in NakhsyVillage,Sinuni Sinjar  with the participation of Haval United Company. Organization WHH

Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Havalunitedgroup@yahoo.com

Construction
2 Project of rehabilitating electric power transmission line Kirkuk-Baiji    400 K.V

 

Directorate General of Electric Power Transmission -Northern Area.

Eng.Fadel Abbas /General Manager

009647507991121

northtransmissionoffice@yahoo.com

Transmission Line
3 ConstructionRoad4.7KminjelokaSpindaryVillageDuhokGovernorate  with the participation of Haval United Company. Directorate of maintenance of roads and bridges Dohuk / Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Havalunitedgroup@yahoo.com

Construction
4 Project of rehabilitating the secondary Altahreer station 132K.V, Iraq-Nineveh-Mosul in the manner of Joint Venture  (J.V) with Mado Company for Electric Contracting (UNDP) Organization Rehabilitation of 132 k.v substation.
5 Project of implementing civil works of the roof, foundations, and chambers of the auto-generating station in Alkasik refinery in Nineveh governorate Iraqi Oil Ministry – North Refineries Company.

Implementation with Kwinz Company Handels&Produktions. GmbH (Subcontractor).

Eng. Khalid Jodi / KUNZ/Iraq branch manager.

 009647823468217

k.joode@kunz-gmbh.net

Civil works
6 Project of rehabilitating the secondary Alsharqya station 132 K.V, Iraq- Nineveh governorate- Mosul, in the manner of Joint Venture  (J.V) with Mado Company for Electric Contracting (UNDP) Organization Rehabilitation of 132 k.v substation.
7 Rehabilitation of Water Supply System of Semahla& Amar Kubr villages, Amar bet village, and Shihiavillag–Wana sub-district with the participation of Haval United Company. Organization L.W.F/             Haval United Company

Authorized Manager:

Jasim  Mohammed  Hassan

009647503661163

Havalunitedgroup@yahoo.com

Construction
 

 

 

 

8

 

 

 

Supplying and implementing potential difference feeders (33K.V) from Almansour secondary station 132 K.V to the station of Aldawwasa 33-11 K.V, Iraq-Nineveh- in the manner of Joint Venture  (J.V) with Mado Company for Electric Contracting (UNDP) Organization Supply and installation underground 33 k.v cable.

 

6- Saheel Almortajez Company projects for the year 2019.

# Project name & Country

of Assignment

Client & Reference Contact Details Types of activities undertaken
1

 

 

Contract of supplying two (2) circuit breakers (33 K.V) type Siemens for the gas electric station of Aldibis. Directorate General of Electric Power Production -Northern Area

Eng. AbdlsameaAbdlkarimHosean

+964 7701322158

diasafe1992@yahoo.com

Electrician
2 Project of implementing civil works of the roof, foundations, and chambers of the auto-generating station in Alkasik refinery in Nineveh governorate Iraqi Oil Ministry – North Refineries Company.

Implementation with Kwinz Company Handels&Produktions. GmbH (Subcontractor ).

Eng. Khalid Jodi / KUNZ/Iraq branch manager.

 009647823468217

k.joode@kunz-gmbh.net

Civil works
3 A project to implement the rehabilitation works for the Nineveh gas station – Baiji Thermal Power Station line

 400 K .V

Directorate General of Electric Power Transmission -Northern Area.

Implementation with Company of  Ummat Al-Salam for Trading and General Contracting (Subcontractor ).

 

Gen. Manager: Muthanna KittanOudah

009647700007165

009647700070771

ummetalsalam@yahoo.com

Transmission Line
4 Project of implementing the rehabilitation of the electric power transmission line in east of Mosul- Tahreer  132 K .V Directorate General of Electric Power Transmission -Northern Area.

Implementation with Company of  Ummat Al-Salam for Trading and General Contracting (Subcontractor ).

 

Gen. Manager: Muthanna KittanOudah

009647700007165

009647700070771

ummetalsalam@yahoo.com

Transmission Line
5 Removing all containers of pipes and pumps in 91-

Qayyarah oil fields.

Sonangoli-raq.com

Sonangol P&P Iraq

contracts@sonangoliraq.com

Mechanical work

7- Saheel Almortajez Company projects for the year 2020.

# Project name & Country

of Assignment

Client & Reference Contact Details Types of activities undertaken
1 Removed all the scrap in the field and move it to 1 location inside the Qayyarah oil field. Sonangoli-raq.com

Sonangol P&P Iraq

contracts@sonangoliraq.com

Mechanical work